DateProject Schedule
Q4 2016Geotechnical Studies at Kinosis project site
Q1 & Q2 2017Environmental Field Studies at Kinosis project site
Alberta Environment & Parks Public Land Acquisition Application
Alberta Consultation Office guidance on Indigenous Consultation
Q3 2018Submit Approval Application to Alberta Environment & Parks
Submit Development Permit Application to RMWB
Stakeholder Engagement & Project Open House
Q3 2019Construction is estimated to start within 1 year after approval is received from AEP for Provincial Environmental Approval and Land Acquisition as well as RMWB for Municipal Development and Building Permits
Q3 2020Mechanical Completion
Q4 2020Startup & Commissioning